Pune Metro fast-tracks work on 11-km stretch to meet December deadline

Gautam Birhade, executive director, Pune Metro Rail and in-charge of the Reach 1 and Reach 2 stretch of the metro route, said the stretch from PCMC to Bopodi is 45 per cent complete. The foundation of 317 of the 456 pillars is complete, and 256 pillars and 163 pillar caps are ready, he said.